# Reconstruction begins at Osh’s Sulaiman-Too complex as two museums close temporarily
- URL: https://economist.kg/en/osh-starts-sulaiman-too-reconstruction/
- Published: 2026-11-24T05:18:45.000Z
- Updated: 2026-11-24T05:18:45.000Z
- Description: The main building’s exhibition hall remains open. $12.5 million has been earmarked for the complex’s restoration and modernisation.
- Author: Азиза Капар кызы
- Tags: Общество, #en

**The Sulaiman-Too Museum and the Cave Museum in Osh temporarily closed to visitors on 23 November 2026 for reconstruction work at the national historical and archaeological museum complex. The exhibition hall in the main building remains open as usual, Kyrgyzstan’s Ministry of Culture said.**

The first phase of reconstruction began on **21 November**. Construction equipment was delivered to the site, and contractors began preparatory work.

Before work began, the complex’s director general, **Mederbek Aparkhanov**, inspected the site with **Shailoobek Arynov**, coordinator of the Regional Economic Development Project covering Osh region and Osh city, and contractor representatives. They discussed the planned work.

> The Ministry of Culture said construction and restoration work would comply with the heritage protection requirements applicable to Sulaiman-Too, a UNESCO World Heritage Site.

> Specific dates for completing the reconstruction and reopening the two museums have yet to be announced.

#### **$12.5 million earmarked for Sulaiman-Too reconstruction**

**Economist.kg** previously [reported](https://economist.kg/potok-grantov-i-kreditov/2026/06/30/vsemirny-bank-sulayman-too-uzgen/) that **$12.5 million** had been earmarked for restoring and modernising the Sulaiman-Too historical and archaeological complex under a World Bank project. A further **$3.5 million** was planned for a new museum building next to the Uzgen Minaret. Combined funding for the two sites was estimated at **$16 million**.

**The Sulaiman-Too reconstruction project includes the following work.**

- Upgrading lighting across the museum complex
- Restoring the Cave Museum
- Landscaping and planting around the mountain and at its base
- Restoring the historic bathhouses for use as a separate museum attraction

Project preparation required coordination with UNESCO specialists because of the mountain’s protected status and the historical significance of the sites on it.

> Authorities previously said they aimed to complete the complex’s modernisation by **2028**. Specific reopening dates for the museums affected by the current phase of work have yet to be announced.

---

For economic news from Kyrgyzstan, follow [Economist.kg](https://economist.kg/) on [Telegram](https://t.me/economist%5Fkg?ref=economist.kg) and [WhatsApp](https://www.whatsapp.com/channel/0029VaUvVed5q08WZEioIN2D?ref=economist.kg). We are also on [Facebook](https://www.facebook.com/economist.kg), [Instagram](https://www.instagram.com/economist%5Fkg/?ref=economist.kg), [Threads](https://www.threads.net/@economist%5Fkg?ref=economist.kg) and [X](https://x.com/economist%5Fkg?ref=economist.kg).